Sungai Selangor Water Supply Scheme
- Phase 2 : Stage 1 & 2, Bukit Badong Treatment Works
FACT SHEET
Location
Bukit Badong, Selangor
Owner
Puncak Niaga (M) Sdn Bhd
Consultant
SMHB Sdn Bhd and Ranhill Bersekutuan Sdn Bhd
Completion Date
Stage 1 : October 1998
Stage 2 : April 2000
Stage 1
a) Reservoir
Shape of Reservoir : Rectangular (Clear Water Tank)
Capacity : 20 ML
Concrete Volume : 13,300 cu.m
Earth / Rock Volume : 168,600 cu.m
b) Pipeline
Type : MSCL Pipeline
Diameter : 2,100 mm
Length : 11,700 m
Stage 2
a) Reservoir
Shape of Reservoir : Rectangular (Clear Water Tank)
Capacity : 20 ML
Concrete Volume : 12,200 cu.m
Earth / Rock Volume : 14,900 cu.m (Incidental Excavation) TOTAL?

b) Pipeline
Type : MSCL Pipeline
Diameter : 2,100 mm
Length : 1,800 m